Utility problems among factors for delayed, abandoned private housing projects

9 May 2023, 10:04 AM
Utility problems among factors for delayed, abandoned private housing projects

PETALING JAYA, May 9 — Utility problem, apart from financial problems facing developers, has been identified as one of the factors for 95 private housing projects in the country to be left abandoned or not completed within the stipulated period,

Deputy Minister of Local Government Development (KPKT) Akmal Nasrullah Mohd Nasir said the utility problem involved electricity supply connection, sewerage system, water supply, road and drainage facilities.

This was identified through a detailed tracking of the data of licensed housing projects carried out during the first quarter of this year.

"So to ensure proactive action at the KPKT level, we will hold discussions with the relevant agencies to find the best solution to resolve the problems,” he told a press conference on problematic and abandoned private housing projects at the headquarters of the 1Malaysia People's Housing Programme (PR1MA), earlier today.

Aa total of 80 private housing projects that were categorized as 'sick' have been completed and issued the Certificate of Completion and Compliance (CCC), from December 31 last year until last March 31.

Akmal Nasrullah said the work progress on the construction of another 12 projects was now back according to schedule.

"This brings the total number of housing projects that have been removed from the list of sick projects for the first quarter of this year to 92 with a value of about RM5 billion," he added.

As for projects handled by PR1MA, eight projects have been completed and issued with the CCC up to April 30, almost reaching the target of 10 out of 20 sick projects set by the ministry to be completed this year.

Regarding the injection of RM29 million in funds allocated through the 2023 Budget to restore sick and abandoned housing projects, Akmal Nasrullah said the ministry’s Task Force on Private and Abandoned Housing Projects would focus on rehabilitating housing projects costing below RM300,000 per unit which are nearing completion.

— Bernama

What do you think?

Latest
MidRec
Media Selangor
About Us

Media Selangor Sdn Bhd (MSSB), a subsidiary of Menteri Besar Selangor Incorporated (MBI), is the official media agency of the Selangor State Government. In addition to the Media Selangor news portal (formerly known as Selangorkini & Selangor Journal), Media Selangor also publishes newspapers in Mandarin, Tamil, and English.

Properties
MS: f922288e558c3b7b1d99bd47484377b4
EN: cd68e718a4d41dc8ef70c9d27c60e1f1
ZH: 100cdec69db9bc7fd9f175cab704a072
TA: 7b60ca9b9b7a9838dc33c5db6fb6f38c
TV-MS: 5c53513d790774360d169f98c36ce619