Jendela: Govt mulls legal action against idle contractors

16 Jul 2024, 9:41 AM
Jendela: Govt mulls legal action against idle contractors

KUALA LUMPUR, July 16 — The government is considering legal action against contractors who fail to complete telecommunication tower projects under the National Digital Network Plan (Jendela).

Deputy Communications Minister Teo Nie Ching said this is due to the unsatisfactory performance of contractors, including those involved in tower construction projects in Sabah.

“We are considering a few measures, including imposing liquidated damages, requiring a performance bond, rejecting claims, and taking legal action under the Communications and Multimedia Act 1998,” she said.

Teo said out of the planned 651 towers in Sabah, only 294 have been completed.

She was responding to a supplementary question from Riduan Rubin (Independent-Tenom) about action against contractors who fail to complete the tower projects.

Teo said 17 out of the 28 new towers planned under Jendela have been completed in Tenom parliamentary, with 68 towers upgraded in the same area.

She also said 2,450 out of the 3,723 planned premises have been provided with fibre optic access, and remaining projects are expected to be completed in stages in the fourth quarter of 2025.

— Bernama

What do you think?

Latest
MidRec
Media Selangor
About Us

Media Selangor Sdn Bhd (MSSB), a subsidiary of Menteri Besar Selangor Incorporated (MBI), is the official media agency of the Selangor State Government. In addition to the Media Selangor news portal (formerly known as Selangorkini & Selangor Journal), Media Selangor also publishes newspapers in Mandarin, Tamil, and English.

Properties
MS: f922288e558c3b7b1d99bd47484377b4
EN: cd68e718a4d41dc8ef70c9d27c60e1f1
ZH: 100cdec69db9bc7fd9f175cab704a072
TA: 7b60ca9b9b7a9838dc33c5db6fb6f38c
TV-MS: 5c53513d790774360d169f98c36ce619