Problematic Rumah Selangorku project in Morib gets new December completion date

1 Mar 2024, 9:00 AM
Problematic Rumah Selangorku project in Morib gets new December completion date
Problematic Rumah Selangorku project in Morib gets new December completion date

By Yasmin Ramlan

SHAH ALAM, March 1 — The Rumah Selangorku project in Morib, Kuala Langat, which faced years-long delays, is set to be completed by December this year, the State Legislative Assembly was told.

State executive councillor for housing Borhan Aman Shah said the developer, Sentoria Bhd, previously faced issues with the bank guarantee payment, which has since been resolved.

The state and Federal governments have also convened multiple meetings and conducted site visits to the project in question, Rumah Selangorku Pangsapuri Morib Anggun, to monitor its progress and ensure its smooth implementation.

[caption id="attachment_347974" align="alignright" width="363"] State executive councillor for housing Borhan Aman Shah responding to queries during the oral answer session of the Selangor State Legislative Assembly, in the State Secretariat Building, Shah Alam, on March 1, 2024. — Picture by REMY ARIFIN/SELANGORKINI[/caption]

“The delays occurred due to issues with the developer’s payment of the bank guarantee, in which they were originally supposed to pay RM18 million.

“However, thanks to the discretion of the Menteri Besar (Dato’ Seri Amirudin Shari), the state government has granted some flexibility,” he said.

This has allowed the developer to settle the bank guarantee to the respective utility companies, and a new investor is set to inject a significant amount of funds into the project.

Borhan was responding to a question from Morib state assemblyman Rosnizan Ahman on the project’s prolonged delay, which was initially scheduled for completion in 2020.

Previously, on February 20, the councillor said the developer had been given a 50 per cent discount on utility bills following a recommendation by Amirudin to offer some leeway.

He added the project delay mainly stemmed from Sentoria’s change in directorship and a pending new agreement between the company and state government.

Following the new appointment, the state is renegotiating with the developer.

“The previous director promised that it would be completed within a year. However, since there is a new director, we need to review the agreement,” Borhan said.

However, he assured that the state government would monitor the project’s progress to ensure it did not fall under the abandoned and sick projects category.

What do you think?

Latest
MidRec
Media Selangor
About Us

Media Selangor Sdn Bhd (MSSB), a subsidiary of Menteri Besar Selangor Incorporated (MBI), is the official media agency of the Selangor State Government. In addition to the Media Selangor news portal (formerly known as Selangorkini & Selangor Journal), Media Selangor also publishes newspapers in Mandarin, Tamil, and English.

Properties
MS: f922288e558c3b7b1d99bd47484377b4
EN: cd68e718a4d41dc8ef70c9d27c60e1f1
ZH: 100cdec69db9bc7fd9f175cab704a072
TA: 7b60ca9b9b7a9838dc33c5db6fb6f38c
TV-MS: 5c53513d790774360d169f98c36ce619